Materials and Resources (MR)
- Total Available Points for MR: 16
- Total Expected Points for MR: 11
Credit 1 - Material Efficient Framing
Intent
Optimize the use of framing materials.
Requirements
Prerequisites
- 1.1 Framing Order Waste Factor Limit.
Limit the overall estimated waste factor to 10% or less.
Credits
- 1.2 Detailed Framing Documents (1 point).
AND/OR
- 1.4 Framing Efficiencies (maximum 3 points).
OR
- 1.5 Off-Site Fabrication (4 points).
We plan on these 4 points as we will be using panelized construction
- Total Available Points: 5
- Total Expected Points: 4
Credit 2 - Environmentally Preferable Products
Intent
Increase demand for environmentally preferable products and products or building components that are extracted, processed, and manufactured within the region.
Requirements
Prerequisites
- 2.1 FSC-Certified Tropical Wood.
The requirements will be met.
Credits
- 2.2 Environmentally Preferable Products (0.5 point each, maximum 8 points).
We plan on 4 points here.
- Total Available Points: 8
- Total Expected Points: 4
Credit 3 - Waste Management
Intent
Reduce waste generation to a level below the industry norm.
Requirements
Prerequisites
- 3.1 Construction Waste Management Planning.
We will meet this by:
- Investigating and documenting local options for diversion (e.g. recycling, reuse) of all anticipated major constituents of the project waste stream, including cardboard packaging and household recyclables (e.g., beverage containers).
- Documenting the diversion rate for construction waste. Recording the diversion rate for land clearing and/or demolition, if applicable (e.g., on gut rehab project), separately from the rate for the new construction phase of the project.
Credits
- 3.2 Construction Waste Reduction (maximum 3 points).
We plan on 3 points by reducing and diverting waste generated from new construction activities from landfills and incinerators to a level below the industry norm.
- Total Available Points: 3
- Total Expected Points: 3